Skip to main content

Background

In steel mills, coil products emerge from the steel making, the hot rolling, and the cold rolling processes, in that order. The steel making process produces slabs, the hot rolling process produces hot coils, and the cold rolling process produces cold coils. Optimized scheduling is necessary and required for these steps to operate efficiently, but it is too complicated to create schedules for all of these processes at once. A common approach is to handle each process independently, but the operational efficiency of downstream processes needs to be considered while scheduling upstream processes, and the scheduling results of the upstream processes are required as input to the downstream processes. This involves a chicken and egg problem. The following method is used to resolve this difficulty:

  1. First, schedule each process starting from downstream moving upstream and set for each coil the process timings that realizes efficient operations for each of its processing steps.
  2. Next, schedule the upstream processes while considering the process timing, and
  3. Finally readjust the schedule of the downstream processes again using the upstream schedules as input.

We call such multiple process scheduling end-to-end scheduling.

end-to-end scheduling
Fig.1 - end-to-end scheduling

The above figure shows the process flow in the end-to-end scheduling with the horizontal axis as time. In steel mills, a group of coils with the same properties is processed at one time. Such properties include the grades of the steel, the types of galvanizing, the surface treatment types, and so on. The groups of coils, shown as rectangles in the above figure, are called production campaigns. Because the types of production campaigns are different from process to process, the waiting times of the coils at each processing step varies. Therefore, the production campaigns related to each other are planned with longer durations at the downstream processes than at the upstream processes, as shown in the figure.

The End-To-End Scheduling for the Cold Mill Processes

The customers for coil products include customers with strict requirements for due dates, such as car manufacturers. In order to satisfy the requests from such customers, long-term scheduling with low overdue is required. When the steel making processes are being scheduled for a week, most of the downstream processes should be scheduled over a period of about a month, considering the effects of the steel making schedules on the downstream processes.

For the cold mill processes, an efficient ordering of production campaigns needs to be considered at each of the continuous processes where the ends of adjacent coils are welded together to form a single steel sheet. Apart from the continuous processes, there are batch processes that do not involve the campaign ordering problem and that do not affect the operational efficiency of upstream or downstream processes. Therefore, the following four continuous processes among the cold mill process stages are considered in the end-to-end scheduling:

The end-to-end scheduling for the cold mill processes is called the Finishing Line Scheduling (FLS).

The Characteristics of the FLS Problem

The cold mill processes involves the four continuous processes for which end-to-end scheduling is required. In other words, the scheduling at each process must consider the operational efficiency of upstream and downstream processes, and also the process timing of coils at adjacent processes cannot be reversed in time. (This property is called vertical consistency, which insures the process timing is never reversed.) In continuous processes, some production campaigns require setup and involve setup costs and times. Therefore, campaign transitions minimizing setup costs and times are preferred. The coils assigned to each production campaign need to be sequenced with consideration of the efficiency of the continuous processing and the quality of the products. The amount of input data for a one month scheduling horizon is very large, amounting to 5,000 coils for each process step. The output schedule:

Here are some of the reasons that the coil ordering within a production campaign affects the operational efficiency and the product quality: The width differences of adjacent coils must be within an allowable limit because the coils are welded together and big gaps tend to cause breaks at the welded junctures. Large width gaps also causes excessive trim losses, as shown in the figure below. The smaller the width gaps, the better. The thickness difference of adjacent coils must also be as small as possible. The same preferences are involved at the CAL process as regards temperatures. Also, in continuous processes, the rollers are worn by processing coils. Therefore, processing narrower and wider coils in that order creates scars, called edge marks, to appear on both sides of the wider coils. Therefore, the ordering of coils within campaigns has a large influence on product quality.

trim loss and edge mark
Fig.2 - Edge marks and trim loss at continuous processes

The Algorithms

We developed the following algorithms for the end-to-end scheduling for the cold mill processes:

sample
Fig.4 - Sample result

Benefits of the FLS System

The FLS system allows users to realize Available-To-Promise with high accuracy based on the production schedule over one month. As a result of considering operational efficiency at the upstream and downstream processes, the lead times between processes are shortened and inventory is reduced. Unplanned downtimes due to lack of materials arriving from upstream processes are reduced. Reductions of setup costs and improvements of coil quality are also achieved.