Business re-engineering is one of the most important topics
on the agenda of a large number of companies. It has been triggered by
a changing business environment that requires companies to be more
flexible and to react faster. [1] New processes are defined;
existing ones are changed or even abandoned.
These processes are no longer only intraenterprise processes, such as
claims processing in an insurance company or loan processing in a bank.
Multiple enterprises are connecting their tasks together in
interenterprise processes to more efficiently manage their own
processes. The order activity in a production planning process for a
car company, for example, starts the appropriate order entry process at
a parts supplier. Companies may even use common processes to tie
together parts of their various companies to form virtual companies, as
foreseen by NIIIP (National Information
Infrastructure Initiative). [2]
Business processes not only deal with customers; internal
administrative processes are also business processes. A typical example
of such an administrative process is the handling of an expense account
form. An employee fills in the proper information; the form is
routed to the employee's manager for approval and then on to the
accounting department to disburse the appropriate check and mail it to
the employee. Backing up and restoring databases as performed by
database administrators is another administrative process.
One of the key objectives of the re-engineered business processes is to
minimize the time required for execution. In a well-defined business
process, therefore, all unnecessary tasks have been eliminated, and all
tasks are performed with the highest degree of parallelism possible.
These tasks can be performed by different people. Coincidentally,
different equipment with different software is used to perform the
tasks. Thus those business processes are run in a distributed and
heterogeneous environment.
Workflow management systems (WFMSs) provide the
foundation for defining and executing business processes. We will refer
to applications built according to the workflow paradigm as
workflow-based applications.
The creation of workflow-based applications needs a special development
method, which we call process-based CASE
(computer-assisted software engineering). The method we are proposing
in this paper provides a consistent way of developing this kind of
application. The metaphor fundamental to this method is the two-level
programming paradigm of workflow technology, in which programming in
the small is delivered through visual builders, and programming in the
large is delivered via business modeling tools and workflow build time.
The next section introduces the notion of a workflow-based application
by revealing the impact of database and workflow technology on the
structure of applications. The subsequent section summarizes the
benefits of workflow-based applications. Then the following
section sketches some relations and synergy between workflow technology
and object technology. The section after that outlines an application
developer's wish list for a development environment that helps to
efficiently design, implement, and monitor workflow-based applications,
and the succeeding section provides a blueprint of the components of
such an environment. That section is followed by one showing some
aspects of testing of workflow-based applications without requiring the
setup of a complex environment, and then a simple example of how such
an environment could work is given. The last section outlines the
transaction management features of a workflow management system
desirable for further enhancing the flexibility of workflow-based
applications. The paper concludes with a summary.
The notion of workflow-based applications
Figure 1 shows the fundamental steps in the
evolution of the structure of application systems. As depicted in part
1 of the figure, the first application systems built were large
monolithical pieces of code with some internal structuring. The
internal structuring reflected the pieces of infrastructure code that
had to be built by the application developers, in addition to the
pieces of code that implemented the actual logic of the application.
Figure 1
Removal of data dependency. The lower boxes of part 1
reflect some pieces for accessing data. These pieces include, for
example, the handling of data sets, such as opening and closing an
account file, performing the actual physical input and output
operations via the appropriate I/O routines provided
by the operating system, such as reading an account record, or
interpreting the data retrieved according to some inline mapping
information, such as the location and the type of the account number.
Any change to the schema of the data, such as the addition of a field
to a record or a change of access path to the data, requires all
applications that accessed the record to be changed and the data to be
migrated. Therefore, these applications are data dependent.
To reduce data dependency, each application system introduced its own
files holding redundant copies of the "same" data with the
well-known consequences of jeopardizing data consistency.
The management of the information about the data, such as which data
are maintained and where the data are used, is also cumbersome. This
situation became worse over time with the increasing amount of
information.
As a consequence, database management systems
(DBMSs) were developed. [3] Their purpose
was to support the definition and concurrent manipulation of data. Many
changes to the data schema and access paths, for example, can now be
done without impacting the related programs. The body of data becomes a
property in its own right; it becomes a corporate asset. Consequently,
the structure of applications changed to the structure depicted in part
2 of Figure 1.
Removal of flow dependency. The boxes depicted in the
middle of each of the three parts are the application logic blocks that
contain the actual application functions and business algorithms. The
top boxes in part 1 and part 2 show some pieces that are required to
put these application logic blocks together in a form prescribed by the
application. To use a banking application as an example, it would
include bringing the blocks into the correct sequence to first withdraw
money from one account and then deposit it into another account, or
passing the proper data from one block to the next so as to pass the
amount of money to be transferred from the withdraw block to the
deposit block, or assigning the right person to a task based on
application-specific criteria such as the authority of the account
owner.
A change in the assignment of tasks to people, commonly referred to as
staff assignment, [4] in the execution sequence of the
application logic blocks, or the addition of a field to be passed
between the blocks, requires the application to be changed.
Applications are flow dependent.
These changes are cumbersome and generally cannot be performed
fast enough. In addition, the actual structure of the business process
is not known to nonprogrammers. This situation becomes worse with the
increasing demand to adapt to market needs that are changing ever
faster.
Workflow management systems were developed to help overcome these
problems. Their purpose is to support the definition and execution of
business processes. That means that the definition and
execution of the appropriate control and data flow,
the assignment of people to tasks, and the invocation of the
application logic blocks are externalized. By definition, changes to
the process can now be done without impacting the application logic
blocks. The process becomes a property in its own right--it becomes a
corporate asset. [5] The structure of the applications changes
to the structure depicted in part 3. The application becomes a
workflow-based application consisting of a model of the
underlying business process and a set of (flow-independent) application
logic blocks. [6] The abstractions of the elementary pieces of
work in a business process are called activities; the
concrete realizations of these abstractions at process execution time
are referred to as activity implementations. [4]
The application logic blocks correspond exactly to these activity
implementations in a WFMS environment.
The capability of the workflow management system to support the
definition and execution of control and data flow, the assignment of
activities to people, and the invocation of the activity
implementations associated with such an activity is not limited to
splitting up large monolithical applications. It allows the various
activities to be distributed to different computers with different
systems. Different systems may mean different operating systems
supported by the same workflow management system or may mean different
workflow management systems. Workflow-based applications are,
therefore, by nature distributed, heterogeneous applications.
The fundamental benefits of workflow-based applications
In this section the following four fundamental benefits inherent
to workflow-based applications are discussed:
- Flexibility in changing the model of the underlying business process
- Integration capabilities for even disparate applications
- Reusability of activity implementations and process models
- Scalability of application development and execution
Flexibility. The first benefit is based on the
two-level programming paradigm underlying workflow-based applications.
The specification of all flow relation information is, as was already
described, separated from the specification of the logic of the
application functions, that is, the algorithmic aspects of the
application. This separation allows the model of the process underlying
the subject applications to change without affecting the associated
activity implementations. It is the predominant reason why enterprises
are investing in workflow technology today.
Integration. The second benefit is based on multiple
features.
First, the ability of a WFMS to persistently store
the workflow-related execution context of each activity implementation
(that means the containers [4]) and share it between different
activities via the supported data flow features allows for an
integration of activity implementations that is different from the
current standard approach of accessing a joint database.
Second, transaction features tailored toward support in
WFMSs have been proposed (for example, see
References 7, 8,
9, 10,
and 11) to especially allow the integration of
activity implementations that are accessing different
DBMSs into atomic units (in the sense of "all or
nothing") or compensation units (in the sense of "joint
compensation"); see the last section for more details.
Third, the heterogeneity feature currently being worked on by the
Workflow Management Coalition (WfMC) [12]
and NIIIP [2] strives toward support of
cross-enterprise business processes. That support means that each
application part may even be managed by a different vendor's
WFMS. The goal is to enable "virtual
enterprises" not only by supporting cross-enterprise sharing of data
based on the STEP (STandard for the Exchange of
Product definition data) standard (for example, see Reference 13), but
also to share business processes across enterprises and to enable
interoperation of workflow management systems.
Reusability. The third benefit is based on the structure of
workflow-based applications themselves. As elaborated earlier, activity
implementations for process models are typically flow-independent and
free of assumptions about their usage (with the final consequence that
external transaction mechanisms are needed; see the last section).
Therefore, a particular activity implementation can be used in many
different process models. If both the activity implementation and the
workflow manager comply with the WfMC standard for
"invoked applications," [12] the activity implementation
can ultimately be used in many different WFMSs. As a
result, the exploitation of workflow technology stimulates reuse of
code with activity implementations (for proper application logic) as
the granules of code reuse. Whereas the reuse of class libraries,
frameworks, parts, and design patterns is coupled with object
technology (for example, see Reference 14), reuse based on workflow
technology is independent of it.
Furthermore, there is a strong demand for reusing process models
themselves. For this purpose, many WFMSs allow for
activity implementations that are realized as process models, so-called
"subprocesses," thus enabling top-down and bottom-up modeling
of processes that helps stimulate the reuse of process models as
subprocesses.
Industry consortia such as the Object Management Group
(OMG) and the Object Definition Alliance
(ODA), as well as various vendors, are currently
defining reusable components for the purpose of being able to construct
applications out of prefabricated parts. The expectation is that these
components will eventually be sold as off-the-shelf components.
The formation of a joint work group of the OMG and
WfMC indicates that these components will be
specified in a manner such that they can be used as activity
implementations within business process models. This will further help
to promote the paradigm of workflow-based applications.
Similarly, industry interest groups and vendors are in the process of
specifying de facto standards for models of business processes that
apply to particular application domains. These process models can be
reused in particular as subprocesses in enterprise-specific processes.
In this context, it is interesting to note that vendors of standard
software, SAP with R/3** [15] for example,
are currently describing their applications via models of business
processes, making use of workflow management systems so that the
application performs according to the process model. Workflow-based
applications will thus very likely play a major role in this area, too.
Scalability. The fourth benefit of workflow-based applications
is their scalability in terms of application development and
application execution. Scalability allows workflow-based applications
to be used for small applications, such as the management of a
doctor's office, and for large applications, such as the order process
in a manufacturing company involving processes of outside suppliers. At
first glance, one would assume that covering such a broad spectrum
demands specialized workflow management systems that have nothing in
common except a few basic ideas. However, that is not the case. It
seems that the development groups of workflow management system vendors
strive for one system architecture and design that caters to the
demands of small and large applications.
Application development. The development of workflow-based
applications provides scaling through the underlying two-level
programming paradigm, the top-down process modeling capabilities, and
the reuse of process models and business objects.
Developing an application in two separate levels, first, the
development and test of the business process and, second, the
development and test of the activity implementations, reduces the
complexity of the application from a design, implementation, and
testing standpoint. In particular, the parallel development of the
activity implementations, made possible by the fixed interfaces to the
business process, provides for a faster development cycle.
The support of subprocesses allows the top-down development of business
processes. First, the high-level business process is developed and
tested, and then the low-level business processes are developed and
tested. This sequence facilitates the parallel development of business
processes.
Using business objects and reusable process models makes business
process development as well as activity implementation development
easier.
Application execution. Scaling of the application during
execution is facilitated through the workflow manager's execution
environment: subprocesses can be executed on different
servers; workload balancing supports exploitation of the available
resources; dynamic invocation of activity implementations (even on
remote processors) provides flexibility in executing activity
implementations; and distribution of work items allows the assignment
of users to servers to be balanced.
Objects can benefit from workflows
Enterprises are investing today in object technology to improve
the productivity of their programmers and to enable even
non-data-processing professionals to build applications via visual
builders (described in a later section). Here we discuss some of the
benefits object technology might gain from workflow technology and how
workflow-based applications can be built with objects. Note that
vendors of standard software (like SAP) are also
combining object technology and workflow technology (for example, see
References 15 and 16).
Flow-independent objects. One of the underpinnings of
object technology is the insight that robustness of a system is
normally achieved by encapsulating things that might become subject to
changes. So, for example, if the order in which operations are to be
performed can change, or if operations can be added or removed, the
guidelines of object technology consequently recommend a dedicated
control object. That control object encapsulates the scheduling of
various operations. Thus, to achieve robustness via encapsulation, not
only behavior and data must be taken into account (what is usually
done), but also "ordering."
If the last proposition is ignored, following the encapsulation
paradigm tends to hide fragments of the proper business processes in
the implementations of the objects. [17] In this situation not
only the objects themselves become flow-dependent, but transitively so
does each application reusing these objects. In addition, the business
processes (being an asset by themselves) are only partially described
explicitly and externalized to a broader community. In contrast,
implementing objects in such a way that they become flow-independent
will result in component-based applications that are much more
flexible.
Scripting and objects. Building flow-independent business
objects will enforce a clear separation of the more stable behavior of
the business objects from the more dynamic behavior of the business
processes. A business process explicitly describes the rules of how,
when, and by whom the services provided by the various objects are
exploited. An activity implementation within a business process may be
directly realized by invoking a method of an object.
When the statics of a business split from its dynamics, the interaction
between business objects is defined by the process model. The process
model may be perceived as a script prescribing the use of
business objects to reach particular business goals. At run time, the
workflow management system will manage the flow of control and data
between the business objects, will establish transaction boundaries
around them as defined in the script, and will make certain that the
proper organizational units of the enterprise become responsible for
utilizing the services provided by the various business objects. Note
that languages like C++ follow a similar philosophy. A program consists
of objects and procedural elements explicitly describing the control
flow between the method invocations of the objects.
It is important to note that we do not consider workflows as a
substitute for scripting languages such as
REXX, [18] LotusScript**, [19] or
Visual Basic**. [20] These languages can be considered as
lightweight scripting languages very well-suited for
composing desktop applications for a single end user, perhaps done by
the end user. Defining a workflow can be considered as
heavyweight scripting suitable for composing applications
requiring the collaboration of multiple people distributed throughout
an enterprise. Heavyweight scripting adds such features as parallelism,
heterogeneity, distribution, and context-dependency to the notion of
scripting. The implementation overhead inherent in these features is
the reason why we call this kind of scripting "heavyweight" and why
we think two different categories of scripting have a right to exist.
Workflows in object-oriented analysis and design. Object
technology provides many techniques to capture the dynamic behavior of
an application, for example, collaboration graphs, event flows, timing
diagrams, and interaction diagrams. At an abstract level, they have the
structure depicted in Figure 2, which we call a
message flow diagram. Basically, such a diagram describes the control
flow between method invocations of the participating objects.
Figure 2
Reference 21 points out,
based on this insight, that two principally
different structures of such diagrams can be observed (see Figure
3). Forks represent centralizing
responsibilities, which means that a single object represents the
global control and data flow. The other objects mainly provide
utilities. Such a structure is preferred by workflow purists.
Stairs represent delegating responsibilities, which means
that each object knows a few other objects and how to exploit them.
Thus, each object is responsible for the local control and data flow
and is thus flow-dependent. Many object purists can be found who prefer
this structure. Our proposition that robustness achieved via
encapsulation must not only regard behavior and data, but also
ordering, is represented by forks that typically encapsulate ordering.
In contrast, stairs express an assumed stability of ordering. It is
obvious that fork and stair structures have to be used in combination
to yield a stable and robust structure.
Figure 3
One of the special strengths of workflow technology is facilitating
modifications for operation orders in an easy manner. Thus, it is only
natural to exploit workflow technology for the implementation of fork
structures, that is, for encapsulating the ordering of operations.
Simply, the controlling object itself becomes an instance of a process
model that in turn describes the control and data flow between the
affected objects.
For this purpose, each method invocation stimulated by the control
object becomes an activity in the process model, which finally
represents the control object. Thus, if the method m of
object o is invoked, o.m() is an activity
of this process model. The control connectors are prescribed by the
time order in which messages are sent according to the message flow
diagram. If m1 is sent to o1 and m2 is
sent to o2 and no other message is sent to any other object
in between, the flow of control is from o1.m1() to
o2.m2(). Based on the structure of message flow
diagrams, no parallelism is exploited in the process model derived by
this simple algorithm. Typically a design phase needs to be conducted
to establish a more sophisticated process model.
At run time, the WFMS will instantiate this process
model, resulting in an instance of the control object. By definition,
there will be no implementation of the control object in the classical
sense, for example, in C++: the implementation consists of the
process model, which is interpreted on a per instance basis by the
WFMS. Consequently, changes to the process model
will immediately affect the implementation of the corresponding control
objects instantiated after the changes.
A method has been proposed in Reference 6
for analyzing a message flow
diagram in order to divide it into a collection of subdiagrams, each of
which is either a fork structure or a stair structure. Fork structures
can be transformed into skeletons of process models in a
straightforward manner. Stair structures are natural candidates for
modularization; that is, they can be realized as programs or as
subprocesses.
Application developer's wish list
The development of workflow-based applications can be facilitated
by a new approach that helps application developers in the design,
implementation, and testing of those applications. We call this
approach process-based CASE to indicate that the
goal of the proposed CASE method is to create
applications that are workflow-based, thus implying that the underlying
business process is externalized and managed by a workflow management
system. This approach is different from the notion of
process-centered CASE, where processes
are used to develop applications and coordinate development
teams. [22] In fact, process-centered CASE
could also be applied to process-based CASE.
First, the development of the applications should be supported with the
set of new and evolving programming paradigms, such as visual
programming, the construction from parts, the usage of business
objects, binary code reuse, object orientation, and, by definition, the
exploitation of workflow.
- Visual programming supports the development of programs
that are no longer performed by writing statements in a programming
language. The program is constructed (1) by creating the advanced
graphical user interface of the program by drawing the screen layouts
on the screen, and (2) by visually assembling and connecting parts to
define the behavior of the program.
- Construction of parts is a technology to build applications
from existing, reusable software components called
parts. [23] The assembly is typically performed via
the composition editor of the visual builder. Parts provide a wide
range of capabilities, from very simple functions through complete,
highly sophisticated applications. Primitive parts can be
combined to form more complex composite parts.
- Business objects are becoming increasingly important as
granules of reuse. Typical examples may be a customer business object
or an account business object. Standardization is underway as shown
earlier in the third section of this paper.
- Binary code reuse is a key factor in the success of
application development productivity. Source code reuse just will not
render the productivity increase the software industry is looking for.
Business objects are the main manifestation of this paradigm.
- Workflow allows us to define, execute, and monitor
applications that move the work to be done to the desktop of the person
responsible for performing a piece of the overall task.
Second, the development approach must cater to the specific
characteristics of workflow-based applications. It must support the
design, implementation, and testing of the distribution aspects of the
applications, in particular, the parallel execution of tasks.
Third, it must support openness through compliance with appropriate
standards, including de facto standards such as
CORBA (Common Object Request Broker
Architecture), [24] OLE (Object Linking and
Embedding), [25] WfMC,
OpenDoc, [24] and Lotus Notes**.
Fourth, this development environment must be available on a variety of
platforms.
And last, the components of the development environment must be tightly
integrated. In particular, they must provide a cohesive, seamless, and
intuitive end-user interface.
Development environment blueprint
The essential components for the proposed environment are (1) a
business modeling tool, (2) an object-oriented analysis tool, (3) a
workflow management system, (4) a visual builder, (5) a database
management system, (6) a database design tool, and (7) object support.
Figure 4 depicts those components that are exposed
directly to the user of such a development system. In this section we
discuss the components.
Figure 4
Business modeling. A business modeling tool is one of
the starting points for developing workflow-based applications. It is
intended to be used by internal or external consultants, organization
specialists, or business re-engineering experts.
IBM's Business Process Modeler, IDS's
ARIS** Toolset, Holosofx's WorkflowBPR
tool, or UBIS's BONAPART** are typical examples of
this type of tool. Their main focus is on allowing the business experts
to model processes and business objects used within a business process.
They typically implement a proprietary methodology to describe the
business process. For example, the IBM Business
Process Modeler uses an extension of the LOVEM*
(Line of Visibility Enterprise Method) methodology developed by
IBM Canada for re-engineering corporations; the
ARIS Toolset uses the ARIS
methodology developed by Scheer. [26]
The usual result of such an analysis is a high-level description of the
business process. On a conceptual level, this high-level process
describes the business actions and their relations, the organizational
units performing these business actions, and the business objects that
these business actions are working on. The level of detail depends on
the significance of a particular item in the overall business process.
A business object therefore could be a complete database, such as the
payroll database, or a single column in a table, such as a state code
used to determine which path needs to be taken within the process.
An important function of business modeling tools is to collect metrical
information about strategic target volumes of business objects and
processes. This information will be refined later in the development
process to determine the performance characteristics of the process as
well as the resources, both people and IT
(information technology) resources, required to perform the process.
In general, the results obtained via the business process
modeling tool are not directly usable by a workflow management
system to execute the business processes. They need further refinement
in the specifications of IT resources, such as
programs used to perform the activities, the topology of the system,
etc. This task is performed using the build-time component of the
workflow management system. The approach is similar to the one taken in
the design of databases, where it starts with a conceptual design that
is transformed into a logical design. The conceptual design, for
example, done as an entity-relationship model, provides an
implementation-independent view of the data. This model is then
translated into a logical design, such as the tables of a relational
database system, by adding implementation-dependent information.
How the information is handed over to the workflow management system is
a matter of coupling the business modeling tool and the workflow
management system. One approach is to have a common data store. A
simpler approach is the generation of an interchange format that is
imported into the workflow management system. The
WfMC is standardizing this format to facilitate the
interchange of process model information between different
implementations of workflow management systems. Until this standard is
issued, the business modeling tool must generate the workflow
manager's proprietary exchange format, such as the FlowMark Definition
Language (FDL) of IBM's
FlowMark*. The ARIS Toolset, for example, generates
FDL from its process definitions.
Object-oriented analysis. Another approach to the development
of workflow-based applications is object-oriented analysis and design.
As outlined previously, the results of the analysis could be used in
different ways. It could be used to generate process skeletons in the
workflow manager's exchange or, if available, in a standardized
format. It could also provide the visual builder with the proper
information to allow rapid creation of the activity implementations.
Workflow build time. The purpose of the build-time component
is to allow the user to define the processes in terms of process logic,
associated organizational information, and IT
infrastructure required to execute the processes. [4,5] As
pointed out earlier, this information may be derived from information
collected by the Business Modeling Tool or the Object-Oriented Analysis
Tool. The definition of the information is entered via a graphical
end-user interface. Typically an animated process graph is used to help
determine the correctness of the process graph and the correct
invocation of the programs implementing the system program. Analytical
and discrete simulation help to determine whether the organization is
capable of handling the workload and whether the IT
resources are sufficient to cope with the system, database, and
communications load. [27]
Visual building. A visual builder is a visual programming tool
that can help develop all kinds of applications, including
mission-critical applications. It allows a programmer to rapidly
prototype and build applications with menu bars, entry fields, and
icons. Programs are written simply by making connections between
objects and parts.
Workflow run time. The run-time component of the workflow
management system controls the execution of process instances. It
allows the user to start, terminate, suspend, and resume processes. It
determines who should perform a particular activity, puts the resulting
work item onto the work list of the selected user(s), schedules the
proper program when a work item is selected and determines what
activities come next after one has been completed, and records all
these actions in an audit trail.
Process monitoring. Processes must be monitored for various
reasons: (1) to determine the workload of people and take proper action
if the workload is unevenly distributed, (2) to recognize critical
situations where work is piling up, and (3) to obtain process
statistics. The process statistics are created from the audit trail
that is automatically written by the workflow management system during
process execution. This information can be used to verify the
assumptions used during simulation, such as process creation rates,
path selection probabilities, and activity processing time.
Schema creation. The business objects identified during
business modeling or object-oriented analysis are the input to
conceptual data modeling. They represent the local conceptual schema of
the application implemented via a business process. In general, these
objects form the kernel entities of the enterprise data model and thus
provide the basis for the creation of an enterprise data model through
view integration. [3,28]
The conceptual schema is transferred into a logical schema, the schema
of the database in which the data are stored.
Reference 28 outlines the
rules for transferring an entity-relationship schema into a relational
schema.
A physical schema is created from the logical schema by choosing
specific storage structures and access paths to achieve optimum
performance for the various applications. Input to the physical schema
design consists of the transaction load and the database load. Both
pieces of data can be derived from information collected during
business modeling, workflow definition, and application
building. [27]
Database monitoring. The activities in the databases must be
monitored to detect performance bottlenecks. Monitoring could trigger
modifications of the database schemes. It is also conceivable that it
may impact the structure of the business processes.
Verification of workflow-based applications
The underlying business process of non-workflow-based applications
is, as outlined previously, deeply buried in the application itself.
That means the business process and the application logic need to be
tested together. In workflow-based applications, the business process
and the programs implementing the activities are described separately.
Testing workflow-based applications, therefore, is much simpler, since
to a large extent the testing of the business process can be done
independently of the testing of the activity implementations. In fact,
the testing of the business process can be done before the actual
implementation of the application functions starts. As soon as testing
of the business process is completed, the interfaces for the control
and most of the data relevant to the data flow are defined.
The verification of workflow-based applications is performed in three
phases, as shown in Figure 5. The first step checks the
process models for correctness. It includes checking to see whether the
process structure, the invocation of programs, and the distribution of
work are correct.
Figure 5
What needs to be checked and what can be checked for correctness of the
process structure depends on the underlying process
meta-model. [29] In the case of IBM
FlowMark, for example, no checks need to be performed for loops since
the process graph is a directed, acyclic graph. But two basic items
always need to be checked. First, the passing of data from one activity
to a subsequent activity must be correct and complete. Incomplete data
lead to an incorrect evaluation of transition conditions, resulting in
incorrect control flow and the passing of incorrect data to invoked
programs or subprocesses. This item is particularly important for
activities where a field in the input container is the target of
multiple data connectors. Second, the transition, exit, and start
conditions must be semantically correct.
The invocation of programs includes not only defining the proper
invocation mechanism, but also properly passing data to the program and
returning the appropriate data.
A staff assignment identifies the set of people who must perform the
appropriate task for each activity. Therefore, checking the correct
work distribution involves not only seeing whether work is assigned to
the right person, but also obtaining a first hint of whether the work
is distributed properly.
IBM FlowMark, for example, uses the technique of
animation to help the process modeler perform this
task. [30] It offers two modes, process debugging and the
regression test. In the process debugging mode, the user navigates
through the process model step by step. In the regression test mode, a
stored script is automatically executed. The execution of the
appropriate programs is simulated by displaying the input to be passed
to the program and allowing the user to fill in the data to be returned
by the program; thus, the programs must not have been implemented. The
advantages of the animation are: (1) the identical presentation of the
process model is used for modeling and debugging, (2) the visualization
of control and data flow as well as the status display of activities
allow design errors to be easily recognized, (3) animation can be done
at any time, even if the process model is syntactically and
semantically incorrect, (4) the work list of the process participants
is visualized, and (5) the interaction in the process debugging mode
can be stored to be used in regression test mode.
In a second step, the process models are checked to see whether the
organization as well as the IT infrastructure is
capable of supporting the number of expected process instances. The
technique used for this phase is simulation: analytical and
discrete.
Simulation is based on metrical information that is collected for the
process and the activity level and is mostly provided by the business
analyst. The process-level information includes the number of processes
started, the probability that a certain branch is taken in the process,
the probability that an activity is repeated, and the size of the
process input and output containers. For the activity, it includes
process-related information, such as the average time required to
perform the activity, including idle and wait time.
Analytical simulation is used to calculate the required people and
computer resources. If this turns out to be insufficient, any further
analysis is superfluous. The sufficiency of computer resources is
evaluated by determining the CPU load on servers and
clients, the network traffic caused by server-to-server communication
and data passed from one activity to the next, and the transaction load
on the database and the transaction processing (TP)
monitors. People resources are calculated by determining the amount of
time required to perform the activities. The information derived for a
process is then combined with the resource information derived from
other processes.
Discrete simulation is used to determine the impact of multiple process
instances competing for the same resources. Input to the simulation
consist of scenarios describing which process models should be used in
the simulation. The simulation component uses this information to drive
the navigation engine of the workflow manager with the proper requests,
such as process start and activity completion. The results are written
to a file that serves as input to create the simulation results.
Typical results are the probability distribution of process execution
time and transaction rates.
The results of analytical and discrete simulation can be used to tune
the accessed databases. Using the activity invocation rates and the
database accesses of the activity implementations, one can determine
the number and types of structured query language
(SQL) calls against each database. This information
and the current or estimated size of the databases provides sufficient
input to the physical database designer to determine the proper
database characteristics. Furthermore, it allows a user to determine
how the size of the database changes over time. Collecting additional
information, such as the distribution of keys, allows, for example, the
detection of hot spots in tables.
The process performance monitor, by analyzing the audit
trail, helps to obtain information relevant to the process performance,
such as the average process duration, idle time for activities, or
excessive notifications when work is not performed in a timely manner.
A sample scenario
This section discusses some of the components of the development
environment in more detail and outlines how those components could
collaborate. IBM products have been selected for
purposes of illustration. The components being explored further are the
business modeling tool, the build-time component of the workflow
management system, and the visual builder. The corresponding products
are the IBM Business Process Modeler, FlowMark, and
VisualAge C++*, respectively.
A simple loan process is used as a guide through the various
components. The loan process starts when a customer contacts the bank
and finishes when the customer receives the appropriate response from
the bank, either a denial of the loan or the granting of the loan.
Business modeling tool. The design of a business
process can start, as outlined earlier, with a business modeling tool.
The IBM Business Process Modeler implements an
extended version of the IBM LOVEM methodology.
LOVEM focuses on the interactions between the
customer and the company. All information is captured via a graphical
editor that supports the creation of two sets of diagrams: hierarchical
structure diagrams and line of visibility charts. Hierarchical
structure diagrams provide a hierarchical grouping of all relevant
elements, such as processes, critical success factors, computer
programs, organizational units, opportunity areas, problem areas, and
line of visibility charts.
There are four different types of line of visibility charts
(LOVC). The architecture LOVC
(ALOVC) provides an overall view of what the company
does, together with the essential customers and the sequence of
business processes. The job LOVC
(JLOVC) shows all activities of a job and provides
the base for analyzing the efficiency of job performance. The logical
LOVC (LLOVC) provides a
refinement of the ALOVC and shows the data flow
between processes and subprocesses. The physical
LOVC (PLOVC) shows the activities
within a business process and how they are performed by connecting
activities to other activities or to document storage, office systems,
and computer systems, for example.
The charts are organized into horizontal areas, called bands. In
LLOVCs, a band represents a business function within
the company, such as personnel. It shows what processes are performed
by each function and the relations between the processes in the form of
data flows, which represent data that are generated from or required by
the process. In PLOVCs and
JLOVCs, a band represents organizational units and
contains for each organizational unit the activities, tasks, systems,
critical success factors, and other aspects of a business process and
the relations between those items in the form of information flows.
Information flows represent the flow of information, but also of goods
and controls.
Figure 6 shows the PLOVC of the loan
process. The horizontal bands represent the parties involved in the
process: the customer, the loan officer, and the loan supervisor. The
line between the customer and the company is called the line of
visibility. The manual and automation bands are used to describe
how a particular activity is supported. When the activity is in the
manual band, it is performed manually; when in the automation band, it
is completely performed by a computer program; when on the line, it is
performed by a computer system that interacts with the user. The system
shown in the figure is used to collect loan information for a customer.
Based on the amount of money involved, an assessment must be made by
the loan supervisor. Finally, the customer receives a loan contract or
rejection letter.
Figure 6
Workflow build time. The business modeling information
must now be made available to the workflow management system. As
pointed out in the earlier subsection on business modeling, it is done
via an interchange format. The business modeling tool converts the
PLOVC of the loan process into FlowMark Definition
Language, which is then imported into FlowMark. This process skeleton
must then be enriched with information required during process
execution, such as program names, staff resolution expressions, and
data structures and data connectors. This type of information, which is
related to information technology, is not collected during business
modeling. The amount of information to be added depends on the amount
and granularity of the information collected by the modeling tool.
Because the activities specified with the business modeling tool are
generally quite coarse-grained, as is the case with the
IBM Business Process Modeler, they often need to be
replaced by subprocesses or a set of activities. Figure
7 shows the loan process after making these
modifications with the FlowMark process model editor. The single system
used in the PLOVC for managing loan information has
been split into multiple smaller programs. The activity
"CollectCustomerInformation" obtains the customer number. If the
customer is new, all customer information, such as the address, is
collected in the activity "CollectCustomerData." The next step,
common again for all customers, is the collection of credit
information, such as the amount of credit.
Figure 7
It should be noted that the program could have been implemented as one
large program. The decision to break up the program has been guided by
the desire to extract control and data flow, in the spirit of workflow,
to make future changes simpler. The one possible disadvantage is the
amount of time required by the workflow manager to navigate through the
process graph, and it can be eliminated by compiling parts of the
process graph. [31] Note explicitly that this function is not
part of the delivered FlowMark product.
When the credit amount is small, and the customer risk factor is low,
the loan is accepted right away, and the activity
"CreateAcceptanceLetter" is started automatically. In the other
case, as already shown in the PLOVC, management
approval must be obtained. On the basis of what management decides, the
loan is either granted or denied.
Testing of the application is performed using the animation facility of
FlowMark, as described in the previous section.
Visual builder. A visual builder, discussed earlier, is the
preferred tool for constructing activity implementations. More
information about IBM VisualAge can be found in
References 23 and 32.
Visual builders allow applications to be constructed from existing,
reusable software components called parts. Parts are either
visual or nonvisual. Visual parts allow an
application developer to easily construct sophisticated graphical
end-user interfaces; nonvisual parts provide programming constructs
such as accessing a database or maintaining a list of text strings.
A part in VisualAge C++, for example, is a software object implemented
as a C++ class that supports a simple, standardized protocol. This
protocol supports the interconnection of parts to form higher-function
parts or entire applications. The part interface is composed of three
distinct features: attributes, actions, and
events. These features correspond to a natural way of
viewing parts (and objects in general) in terms of what properties
(attributes) they have, what behaviors (actions)
they can perform, and what unsolicited information (events)
they can provide to other parts.
The construction of the application is via the composition editor of
the visual builder. The editor provides the capability to create the
views for the application, to select the parts that implement the
logic, and to make connections between the parts.
The workflow management system provides an application interface so
that the activity implementation can access the input and output
containers of the activity. The construction of workflow-based
applications via visual builders is simplified through nonvisual parts
for the input and output containers that wrap the latter.
Reference 33
shows a method for creating those parts from the container structures.
Figure 8 illustrates the construction of the program
that implements the loan data collection activity in the loan process.
The window for the composition editor shows two data entry parts for
displaying the customer's first name and last name and two data entry
parts for entering the credit amount and the risk factor. The two
nonvisual parts reflect the input and output containers of the
activity. The arrows between two parts indicate that the change of one
part attribute should be propagated to the attribute of another part.
The arrows between the input container part and the first name and last
name fields cause the fields on the screen to be filled with the
appropriate field from the input container. The arrow between the
address and the credit amount fields and the output container causes
the address and credit amount fields to be put into the activities
output container. The arrows between the input and the output container
part cause the first name and the last name attribute of the input
container part to be copied to the output container part.
Figure 8
Another application programming interface standardized by the workflow
management coalition is the work list handler application programming
interface. This interface allows application developers to replace the
workflow manager's standard interface for managing work lists,
starting work items, and starting, terminating, and suspending
processes with a custom-designed interface. The visual builder can
facilitate the development of these interfaces by using parts that wrap
the work list handler interface.
Further integration points between the visual builder and the
build-time facility of the workflow manager are conceivable. For
example, honoring each other's drag and drop procedure would allow an
activity to be dropped on the icon of the visual builder, which
automatically opens the composition editor and puts the appropriate
input and output container parts on the surface.
Transaction management for workflow-based applications
Activity implementations can be not only transactional programs,
or classical transactions, but also nontransactional programs. For
historical reasons, transactions as activity implementations frequently
appear when the encompassing process model represents one of the core
business processes (order entry, etc.) of an enterprise, and
nontransactional activity implementations are frequently found within
support processes (travel expense accounts, etc.). Today it can be
observed that many workflows contain a mixture of transactional and
nontransactional activity implementations. In this respect,
WFMSs are vehicles to connect the world of
transactions and the world of nontransactional programs. The
corresponding programs are "pasted together" unhampered; they are
only restricted by business processes that prescribe the way in which
the enterprise performs its businesses.
When the sophistication of an enterprise in exploiting workflow
technology increases, the requirement for supporting the definition of
work units within workflows appears. The exploiters of a
WFMS suddenly ask for advanced transaction paradigms
that relate to their business processes; they call a business process
that makes use of advanced transaction features a business
transaction or an extended transaction. First, it
encompasses some transactions in the classical sense and combines them
with nontransactional programs, thus extending the scope of traditional
transaction processing. Second, it groups both classical transactions
as well as nontransactional programs together into a unit of work that
reflects the semantics and behavior of their business processes, thus
extending the classical transaction paradigm.
Note that most of the features outlined in this section are not
available in commercial systems. Because of the relevance sketched
earlier, we included this subject as an outlook to possible extensions
of some commercial systems.
A brief sketch of transaction models. For the reader's
convenience, we provide a brief taxonomy of transaction models based on
the duration of the underlying unit of work. More details on
transaction models can be found in References 34
and 35.
The fundamental concept in this area is the ACID
paradigm, which enforces the collection of operations to behave as
follows:
- Either all of them are applied to the system or none of them at all
(atomicity).
- They lead to a new valid state of the system (consistency).
- They do not affect (until explicitly made visible) operations outside
the collection (isolation).
- They are not undone because of any later system failure
(durability).
Tremendous work has been performed in the past to figure out how
the structure and behavior of units of work correlate with their
average duration. As a result, different transaction models have been
proposed.
What is traditionally subsumed under the notion of a transaction is a
flat ACIDic unit of work with a duration of about a
second. Typical application areas for which this notion of a
transaction is best suited are telephone switching, flight
reservations, or accounts handling. Units of work that last for tenths
of a second when using the flat ACID paradigm (like
an order entry application) resulted in the invention of a transaction
model (close-nested transaction) that allows structuring the overall
transaction as a tree of subtransactions, thus improving parallelism
within the encompassing unit of work and enhancing its overall response
time. When huge collections of data items have to be manipulated, as in
batch updates, durations between minutes and hours are found. In this
situation, ACIDicity results in inappropriate
concurrency and recovery behavior that means backing out all
modifications if the last manipulation fails. That led to techniques
like minibatches and savepointing. Incidentally, these techniques
require special programming by the application programmer, such as
persistently tracking the state of the transaction. They are,
therefore, not suitable in more complicated applications such as trip
reservation systems where multiple databases might be accessed and
operations can only be undone semantically by invoking special
compensation actions. Transaction models such as open-nested
transactions, which assume a manual invocation of compensation, or
those such as Sagas, which support system-invoked compensation,
circumvent such restrictions. When units of work last for days, weeks,
or even much longer, an appropriate transaction model must deal with
(planned and unplanned) system shutdowns without losing control of the
boundary of the unit of work, must facilitate partial backout, or must
cope with different users cooperating in the unit of work. The
compensation spheres transaction model to be described shortly is
targeted toward these conditions.
Two categories of transaction functions. When analyzing the
exploitation of workflow technology with respect to extended
transaction processing, the following two independent categories of
features can be identified.
- The WFMS should allow for coupling activities of
business processes with respect to their semantic success.
An activity is successfully completed semantically if the work has been
finished as it was intended by the process modeler. An activity such as
sending an e-mail note, for example, has successfully completed
semantically when the note has been written and sent. If the work
associated with an activity cannot be successfully completed
semantically, or when the results produced by a collection of
activities are detected to be incorrect, the WFMS
should undo the already-processed coupled activities and start the
affected parts of the business process again. Basically, this is the
requirement for a compensation-based partial backward recovery
facility, which is referred to as compensation spheres. Work is undone
either by automatically deriving the business process representing the
reverse execution of the part to be undone or by starting a predefined
business process to repair the situation as described below.
- The WFMS should allow for coupling transactional
activities, meaning activity implementations that represent
transactions in the classical sense, with respect to their
transactional outcome. If one of the transactions fails (in the sense
of the ACID paradigm), the whole collection must be
aborted. Basically, this requires the ability to declare the atomicity
of collections of activities (via an atomic commit protocol, or via
close-nested transactions, etc.). Such collections are referred to as
atomic spheres. A WFMS can manage an atomic sphere
by dynamically creating a common transactional context when entering
the atomic sphere and initiating the atomic commit protocol for leaving
the atomic sphere (see discussion on atomic spheres below).
Compensation spheres. It is the nature of business processes
that activities are generally long running (especially in tolerating
system shutdowns) and must be thus interruptible, and that they often
externalize intermediate results. Obviously, the same is true for
business processes themselves. Furthermore, a business process usually
contains collections of activities that are semantically coupled in the
sense that either all coupled activities must be performed successfully
or the work associated with the activities must be backed out to allow
the business process to continue correctly. In this context, the usual
transaction models (generally realized via mechanisms like locking,
etc.) obviously do not apply.
A transaction model, called compensation spheres, suitable
for coping with these requirements has been introduced in
Reference 9,
and the reader is referred to that publication for in-depth details. A
compensation sphere is any collection of activities of a process model
such that finally either all activities must have run successfully, or
all activities must have been compensated. An activity that has not run
is considered to be compensated via NOP (no
operation, i.e., nothing is performed); that means in practice only the
activities of the compensation sphere that were activated are
physically compensated. Furthermore, each activity within a
compensation sphere or the whole compensation sphere itself is
associated with an activity called its compensating activity. A
compensating activity might be a program or again a process
model. The basic mode of undoing a compensation sphere is to
automatically schedule the compensating activities of all activities
within the sphere in an order that is the "reverse" of the order in
which the proper activities of the compensation sphere have run. Of
course, staff resolution does also apply to the scheduling of
compensating activities.
Figure 9 shows a process model for trip reservations.
After the client plans the itinerary, it is submitted to travel agents
who will try to make the corresponding reservations for hotel rooms,
rental cars, and flights. To speed up the reservation process, these
activities can be worked on in parallel by different people. If all
reservations have been made, the resulting schedule is printed and sent
to the client. If one of the travel agents fails to make an appropriate
reservation (for example, there is no hotel room available for part of
the itinerary), compensating activities are scheduled to cancel the
reservations already made.
Figure 9
Many different parameters affect actual behavior when backing out a
compensation sphere. For example, you can specify whether compensation
should be performed and whether work within affected process branch(es)
should continue at the entry points of the compensation
spheres, whether some administrative actions have to take place, or
whether the control flow simply has to continue at the entry points of
the compensation spheres without performing any compensation.
Furthermore, compensation spheres can become a target of cascading
backouts, and backout is not only performed in a "discrete" manner
by running the compensating activities associated with the proper
activities, but also in an "integral" manner by simply running a
compensating activity (which can again be defined as a process model)
that is directly associated with the affected compensation sphere
itself.
Compensation spheres will provide tremendous benefits from a cost and
re-engineering point of view in automating compensation. Many
enterprises have special departments completely dedicated to
compensation. When erroneous situations are detected, members of these
departments are informed, and they use compensation techniques to
manually repair the broken resources. Long-running transactions will
typically be modeled as compensation spheres.
Atomic spheres. As was described in the third section,
activity implementations are canonical candidates for reuse. It is a
well-known proposition from software engineering that components built
for reuse should have weak couplings. In other words, the number and
complexity of connections between such components should be minimized.
The following example demonstrates this constraint for an activity
implementation dealing with recoverable resources. Because it is
striving for a high degree of reusability, it consequently must not
assume the management of any transaction boundaries. In workflow-based
applications, it must, therefore, be possible to establish transaction
boundaries outside of the activity implementation.
Let us assume two activity implementations, one of which
WITHDRAWs an amount from a particular
ACCOUNT, the other
DEPOSITs an amount to an
ACCOUNT. Note that this could be nicely
implemented as two methods of an account business object. Since a
customer may sometimes wish to put money into his or her account, or
sometimes wish to withdraw money from the account, it is seductive for
the implementer of the DEPOSIT as well as the
WITHDRAW activity implementation to establish a
separate transaction boundary that will commit or roll back the
performed work. The transfer of money from one account to another could
now reuse both the DEPOSIT as well as the
WITHDRAW activity implementation by invoking
WITHDRAW for the first account and
DEPOSIT for the second. It may happen by accident
that the WITHDRAW activity implementation commits,
but DEPOSIT does not leave the overall
"transaction" in a consistent state. This reveals the necessity of
being able to establish transaction boundaries separate from the
activity implementations. It is the WFMS that could
issue independent commit requests for WITHDRAW and
DEPOSIT in the first scenario but could issue a
"global commit" in the second scenario.
Writing components without any assumptions on transaction boundaries
will enhance their reusability. This observation is reflected in
OMG's Object Transaction framework, [36]
which provides access to transaction managers and resource managers. It
allows WFMSs to manage transaction boundaries. For
that purpose we introduce the concept of an atomic sphere.
An atomic sphere is a set of activities each of which is
"transactional" in the sense that they access recoverable
resources. Furthermore, the control flow between two transactional
activities of an atomic sphere must not leave the atomic sphere and
enter it again at a later point in time. The WFMS
will make sure at run time that either all activities that have run
within the atomic sphere are committed or all have aborted (note that
due to different heuristic decisions of two participants [37]
the semantics cannot be enforced). In the second scenario of the above
example, the WITHDRAW and DEPOSIT
requests are defined as an atomic sphere so that the
WFMS will ensure a consistent end-of-transaction
processing.
Note the subtle but important difference to distributed transactions:
Based on the syntactic specification of an atomic sphere within a
process model, it is the WFMS that establishes the
transaction boundaries dynamically (dependent on the execution
context of the workflow). Thus, the activity implementation programmer
is freed from this concern. In a raw distributed transaction
environment, programmers have to deal with it. [38]
At the operational level, each implementation of an activity
within an atomic sphere is required to exploit only resource managers
in the sense of Reference 38 and does not provide its own
end-of-transaction processing.
Atomic spheres might become very helpful from a technical point
of view. They permit, for example, the tying together of independent
(and, in the above sense, well-behaving) transactions that are
manipulating databases in such a way that if one transaction fails, the
others are aborted, too. It significantly simplifies the task of
managing the associated transactions. Nevertheless, atomic spheres
should be exploited very selectively because of their operational
drawbacks. They use a two-phase commit protocol, which inherently
strives toward holding locks until the end of the encompassing atomic
sphere, thus reducing concurrency. In addition, many messages have to
be sent so that there is a consensus to the outcome of all
participating transactions. Both locking and message traffic impact
performance. Therefore, only a few short running transactional
activities should be bound into an atomic sphere.
Mixing compensation spheres and atomic spheres. From a
modeler's perspective, compensation spheres and atomic spheres are
overlaying the model of a business process. The result is that modelers
will specify the processes of an enterprise and identify collections of
activities that have to be explicitly undone in case of an erroneous
situation (in the sense of being repaired via a dedicated business
process) and resumed afterwards. They will also specify collections of
transactional activities that are undone (in the sense of simply
restoring the manipulated resources to their original state) in case
one of these transactions fails. The sphere definitions are stored in
the WFMS with the models of the business processes,
resulting at run time in business transactions or extended
transactions, respectively, managed by the WFMS.
Summary
We have shown that the basic routing features of a
WFMS allow the extraction of all flow information
from an application similar to a DBMS that provides
the means to extract all proper data management functions from an
application. As a result, the application is both data-independent and
flow-independent. Such a workflow-based application consists of a
process model and a collection of activity implementations. The
activity implementations become a subject for reuse to be exploited in
different process models. We have shown how potential transactional
features of a WFMS could further enhance the
reusability of activity implementations. The task of writing activity
implementations is reduced to realizing proper application logic or
business functions. This task can be further eased dramatically by
exploiting visual builders, reusable parts, and business objects.
Starting from an application developer's wish list, we have proposed
an application development method and environment that facilitates the
design, implementation, and testing of workflow-based applications. A
three-phase approach, which includes animation, simulation, and
monitoring, helps to verify the workflow-based application without an
extensive setup of complex environments. A sample scenario showed
partially how such an environment could be used by an application
developer.
Acknowledgment
We thank Ed Vogt for discussing with us many times some of the
ideas outlined in this paper. We would also like to thank Birgit
Schmidt-Wesche, whose comments helped to improve the style of the
paper.
*Trademark or registered trademark of International Business
Machines Corporation.
**Trademark or registered trademark of SAP AG, Lotus Development
Corporation, Microsoft Corporation, IDS Prof. Scheer GmbH, or UBIS
GmbH.
Cited references and note
Accepted for publication September 10, 1996.
|